The owner brought Apex in after a fire damaged the roofing system over Sugar Flats, a 171-unit occupied community in Salt Lake City. The roof was inspected, slope-verified and replaced with a warrantied single-ply system while residents stayed home.
%2520(2).jpeg)
The owner brought Apex in after a fire damaged the roofing system over Sugar Flats, a 171-unit occupied community in Salt Lake City. The roof was inspected, slope-verified and replaced with a warrantied single-ply system while residents stayed home.
Address fire-related damage to the existing roof at Sugar Flats and put a system on the building that keeps water out for the long term.
Replacement alone was not enough. The job needed a full diagnostic inspection, slope verification and a system upgrade to stop future moisture intrusion — on a building where residents stayed home throughout.
Proposed and installed a Versico VersiWeld 60-mil TPO assembly matched to the existing substrates, self-performed by Apex crews with material from Beacon Supply. Apex has since returned for an exterior mezzanine renovation, ADA door replacements, unit repairs and ceiling repairs.
A watertight roof delivered in three weeks and on budget, with a 15-year watertight warranty and no disruption to residents.
Sugar Flats is a 171-unit multifamily property in Salt Lake City. After fire damage to the existing roof, the building needed more than a patch. Apex ran a full diagnostic inspection, verified slope, and upgraded the system to stop future moisture intrusion.
The solution was a Versico VersiWeld 60-mil TPO assembly matched to the existing substrates, self-performed by Apex crews with material from Beacon Supply. The roof was delivered in three weeks, on budget, with a 15-year watertight warranty, and residents stayed home throughout.
Fire-related roof work sits between reconstruction and roofing: the damage has to be documented and repaired, and the new assembly has to perform for the next fifteen years. Our Utah team handles both, for multifamily owners across the Wasatch Front.
5 photographs from the job. Inspection findings and the finished TPO roof.